Revision Radar

Engineering change blast radius, without the usual PLM swamp.

Release
Readiness score98

ECO-2197

Valve body drawing tolerance note cleanup

VGX-42 valve body · Rev FG · CNC machining + CMM

Blockers0
Stale0
Unknown0
Back to sandbox
Blast radius board

Impact map

Redline scope

Clarifies a secondary edge-break callout and aligns drawing notes with the already-running process plan. No geometry or toolpath shift.

  • Edge break note 0.2 max → 0.15-0.20 controlled note
  • Inspection note reordered to match final print
Operational fallout
  • Op-10 face mill
  • Op-40 deburr
  • Final CMM

Work orders: WO-7441, WO-7444 already queued with matching traveler text.

External exposure

Supplier: None. Internal only.

Inventory: 122 finished blanks, 18 open kits.

Parts
1
Operations
2
Quality
1
Docs
1
Inventory
1
Artifact register

Impacted objects

ArtifactDomainStatusOwnerDue state
VGX-42 valve body print package
PART-4420
partsReadyDesignReleased
Drawing D-4420 rev G
DOC-781
docsReadyDocument controlStamped
CMM inspection plan IP-4420
IP-4420
qualityReadyQualityAligned
Deburr traveler WI-208
WI-208
operationsReadyManufacturing engineeringCurrent
Open work order WO-7441
WO-7441
operationsReadyProduction controlNo hold needed
Finished valve body lot 77A
LOT-77A
inventoryReadyStoresNo relabel
Revision events

Timeline

24 Apr, 05:10
Redline issued

Design released a note-only markup package.

24 Apr, 07:00
CMM cross-check

Quality confirmed existing plan already enforces the revised note.

24 Apr, 08:40
Traveler audit

Manufacturing traveler text matched the new note verbatim.